What does Assurance Contracts and Pre-Sales conclude, in numbers, about “Rules for Displaying True Progress: Auditing Counts, Deadlines, Remaining Stock and Refunds”?
Answer: Two features of the table deserve attention. First, the straight line overestimates early and underestimates late. On day 3 the planned count is 42 and the straight line gives 196.0, far above the real expectation; on day 12 the planned count is 84 and the straight line gives only 98.0, apparently short, yet with 31.1 orders still expected the chance of success is 0.9989. Second, once the true count falls behind plan, the chance of success drops quickly: at day 10 with only eight tenths of the planned count, 60 orders, the chance is 0.5464; at day 12 with eight tenths, 67 orders, it is only 0.3888.
Scope of the numbers: Parameters are illustrative; all calculations are generated by the book's programs. The book is general analysis, not individualised business or legal advice.
Data table
The numbers below are printed verbatim by the chapter's Python program and can be reproduced by running it. standard-library Python onlyprinted values that match the answer: 0.3888, 0.5464, 0.9989, 10, 12, 196.0
| K = 100 | expected total = 115; P(made) at launch 0.9284 | ||||
| day | m vs plan | m | straight line | rest mean | P(made | m) |
| 3 | 0.8 | 34 | 158.7 | 73.0 | 0.8101 |
| 3 | 1.0 | 42 | 196.0 | 73.0 | 0.9692 |
| 3 | 1.2 | 50 | 233.3 | 73.0 | 0.9982 |
| 7 | 0.8 | 48 | 96.0 | 54.4 | 0.6454 |
| 7 | 1.0 | 61 | 122.0 | 54.4 | 0.9878 |
| 7 | 1.2 | 73 | 146.0 | 54.4 | 1.0000 |
| 10 | 0.8 | 60 | 84.0 | 40.4 | 0.5464 |
| 10 | 1.0 | 75 | 105.0 | 40.4 | 0.9962 |
| 10 | 1.2 | 90 | 126.0 | 40.4 | 1.0000 |
| 12 | 0.8 | 67 | 78.2 | 31.1 | 0.3888 |
| 12 | 1.0 | 84 | 98.0 | 31.1 | 0.9989 |
| 12 | 1.2 | 101 | 117.8 | 31.1 | 1.0000 |
Show the full program
# Chapter 6. p61: what a true progress count says. With the 14-day
# arrival profile of p32 (expected total 115, K = 100), a page that
# shows the real count m after day t lets anyone compute the honest
# chance of success P(N_rest >= K - m), N_rest ~ Poisson(rest of the
# expected total). A straight-line projection m x 14 / t ignores the
# closing burst and reads the quiet middle as failure. Rows: m equal
# to 0.8, 1.0 and 1.2 times the count expected by day t.
import math
K, MU = 100, 115.0
W = [3.0, 1.8] + [0.6] * 10 + [1.4, 2.6]
def pois_tail(k, mu):
if k <= 0:
return 1.0
terms = [math.exp(j * math.log(mu) - mu - math.lgamma(j + 1))
for j in range(k)]
return 1.0 - math.fsum(terms)
if __name__ == "__main__":
wsum = math.fsum(W)
rates = [MU * w / wsum for w in W]
print("K = {} expected total = {:.0f}; P(made) at launch {:.4f}"
.format(K, MU, pois_tail(K, MU)))
print("day m vs plan m straight line rest mean P(made | m)")
for t in (3, 7, 10, 12):
done = math.fsum(rates[:t])
rest = math.fsum(rates[t:])
for f in (0.8, 1.0, 1.2):
m = int(round(f * done))
line = m * len(W) / t
print("{:3d} {:9.1f} {:5d} {:14.1f} {:10.1f} {:12.4f}".format(
t, f, m, line, rest, pois_tail(K - m, rest)))Single source and citation
Fan, Y. (2026). Assurance Contracts and Pre-Sale Group Thresholds: Refund Promises and Free-Riding Equilibria in Public Goods (Version 1.0.0), Chapter 6: Rules for Displaying True Progress: Auditing Counts, Deadlines, Remaining Stock and Refunds. 5D Library. DOI pending
DOI pending · monograph page goes live after publication · 5DL-B-316 · v1.0.0 · CC-BY-NC-ND-4.0
BibTeX
@book{fan2026316,
author = {Fan, Yafu},
title = {Assurance Contracts and Pre-Sale Group Thresholds: Refund Promises and Free-Riding Equilibria in Public Goods},
year = {2026},
publisher = {5D Library},
edition = {1.0.0},
note = {DOI pending}
}Other chapter answers in this book
- Chapter 1 · The Equilibrium List of a Threshold Game: What a Refund Promise Actually Changes
- Chapter 2 · From the Core to Crowdfunding: Refined Theory, Laboratory Evidence and Platform Data
- Chapter 3 · Before the Deadline: Success Probabilities under Poisson Arrivals, Binomial Audiences and Uncertain Rates
- Chapter 4 · The Refund Bonus: Mechanism, Equilibria and Expected Cost of the Dominant Assurance Contract
- Chapter 5 · Where to Put the Threshold: Break-Even, Sensitivity and the Weight of Pilot Data
- Chapter 7 · Classical Sources East and West: "Goods Hate to Lie on the Ground" and Hume's Meadow
- Chapter 8 · Closing the Loop: Operating a Limited Pre-Sale Page, the Calculator and a Pre-Registered Test